Data Center Locations

Picture2

Richmond, VA

1401 Meadowville Technology Parkway

CTP-01 (Fully Leased)

Space: 250,000 sq. ft. existing purpose built data center

Power: 28MW existing

Status: Fully operational

CTP-02 & CTP-03 (In Construction)

Space: 284,000 sq.ft. planned

Power: 120MW

Status: CTP-02 reserved, CTP-03 available from Q3 2025

Picture3

Volo, IL

300 South Fish Lake Road

YLO-01 (Fully Leased)

Space: 160,000 sq.ft. existing purpose built data center

Power: 14MW existing

Status: Fully operational

 

YLO-02 (In Construction)

Space: within exisitng 160,000 sq. ft. shell

Power: 14MW incremental

Status: Reserved, delivery Dec 2024